|
Contents
---
1. Introduction --- 2.
Roadway System
3a. I- 84 --- 3b.
RT 7 South --- 3c.
RT 7 North
4. Projects by Municipality --- 5.
Bus Plan --- 6.
Rail Plan
Other Elements 7a, 7b,
7c, 7d,
7e
--- 8.
Resource Center
For
any transportation project in the Region to obtain a commitment
of federal transportation funds, it must first appear on the
HVCEO maintained lists below:
4A.
BETHEL TRANSPORTATION PLAN
4B.
BRIDGEWATER TRANSPORTATION PLAN
4C. BROOKFIELD TRANSPORTATION PLAN
4D.
DANBURY TRANSPORTATION PLAN
4E. NEW FAIRFIELD TRANSPORTATION PLAN
4F. NEW MILFORD TRANSPORTATION PLAN
4G.
NEWTOWN TRANSPORTATION PLAN
4H.
REDDING TRANSPORTATION PLAN
4I. RIDGEFIELD TRANSPORTATION PLAN
4J.
SHERMAN TRANSPORTATION PLAN
PROJECTS INITIATED BY CONN DOT
In general there are two options for transportation
project development. First, Conn DOT is often the initiator
of improvement projects in the municipality, even without
anyone asking.
On state roadways safety problems must be addressed, turning
lanes added, new signals installed, and maintenance activities
scheduled. These are often at considerable expense and make
use of federal funds received at Conn DOT. So without any
lobbying at all, the municipality receives some improvements.
And when
it comes to these state initiated improvements, mostly to
the state roadway network for which it is responsible, Conn
DOT is very good about seeking local opinions and input. And
in addition, as needs statewide are great and financial resources
are limited, there is little interest in forcing investments
upon an unwilling community.
But ultimately
there may be a difference of opinion, such as the need to
widen from two to four lanes in an area noted for its village
character (such as Ridgefield’s Branchville section
on Route 7), or on the raising of the height of an overpass
that will have the consequence of allowing larger trucks to
pass (as on Route 53 in Bethel).
In these
situations the municipality has recourse to a veto power exercised
by HVCEO under federal law over the regional list of federal
projects known as the Transportation
Improvement Program for the area.
But realistically,
the mayors and first selectmen on HVCEO are not anxious to
stop federal funds that Conn DOT wishes to see flow into the
area. Rather, that their consent is ultimately needed tends
to keep state and local officials cooperating and shaping
projects in their early stages such that they can succeed.
A subset of state projects are those state required but funded
at private developer expense. These types of upgrades are
required when a traffic generator has an impact on a state
roadway, and therefore must help address that impact, usually
thru a combination of roadway widenings, the installation
of turning lanes, and new traffic signals.
PROJECTS
INITIATED BY MUNICIPALITY
While much of the available federal
and matching state financial resources are funneled into Conn
DOT initiated projects, perhaps just as much is applied to
projects for which the initiator is not Conn DOT but the municipality.
This is the second option, a complex process without a single
application form or definitive municipal dollar allocation
as guidance.
At the
outset of determining which congestion relief projects to
pursue, it is important to know that not all must be located
on state roadways. Some local roads, if they are higher classifications
of important collectors and arterials, also qualify for federal
funds.
Also,
non-transit projects that do the most to relieve state roadway
congestion or that facilitate investment in major economic
development receive the most attention from the state. For
large economic development projects, state economic development
agencies and the Governor’s Office sometimes intervene
with Conn DOT.
The best
initial approach is to spend some time up front developing
sound project proposals. HVCEO receives federal transportation
planning funds to assist municipalities with this step.

A critical
component of municipally initiated project development is
to seek the input of Conn DOT transportation professionals
early on, as improvement concepts are formulated.
To facilitate
this process Conn DOT maintains, within its Bureau of Engineering
and Highway Operations, a well organized Project
Development Unit (PDU) to receive and evaluate
such ideas. The PDU required that municipalities submit their
proposals thru the HVCEO, which in this and in other ways
acts as a localized field agent for Conn DOT.
After
review, if the municipality and Conn DOT agree that a project
is worthy, the next question is finding sufficient funds to
design and construct the project. This is, or course, the
hard part. There are multiple
federal funding categories utilized in Connecticut,
each with slightly different rules as to use, and much competition.
One small
category, STP-O, is tied to subarea allocation within Connecticut.
HVCEO and the other regions are empowered by the federal government
to set priorities for this funding source.
A recent example of an STP-O project for Danbury is the central
area coordinated signal system. In Bethel, the new bridge
over Limekiln Brook on Old Hawleyville Road. HVCEO also sets
regional priorities for STP-E, the federal enhancement and
streetscape program.
Since
1990 HVCEO has taken the intermunicipal competitiveness out
of its STP-O decisions by use of a “fair share”
allocation tied to municipal population. But flexibility of
allocation is possible, as when Danbury agreed that Brookfield
could exceed its STP-O fair share for widening of Federal
Road in Brookfield up to the Danbury City Line, as that congestion
relief logically assisted both municipalities.
Federal
funding categories with much larger dollar sums, such as STP-A,
have no mandatory subarea allocation and are thus largely
controlled by the state. Here old fashioned lobbying by the
municipality, its legislators, and HVCEO, is needed. The key
is to have someone in the local government to coordinate the
effort.
Sometimes
projects begin with the more limited STP-O program, and then
stall because that limited category cannot accommodate the
large cost revealed after preliminary design is completed.
Then the municipality can hope to have its STP-O project converted
by Conn DOT to the larger STP-A category. Danbury succeeded
in this approach with the upcoming Mill Plain Road widening.
Coordinated statements and appearances by the legislative
delegation are always valuable. These activities can be aimed
at the level of the Conn DOT Commissioner or the Governor’s
Office.
But it
again must be stressed that it is best to have first shaped
the desired project such that it has the support of Conn DOT
professional staff, as their opinions are given great weight
at legislative hearings. The discussion there can be centered
around a proposed bill that proposes to give direction to
Conn DOT on a particular transportation project.

Even after
some initial progress is made there are still problems. While
smaller scale maintenance projects usually proceed to construction
by their own momentum, such movement is never common with
the larger cost roadway capacity oriented projects.
These
may at first proceed relatively smoothly through their design
phase. But then advancing to the more costly construction
phase is stalled, and another lobbying phase is needed.
This halt
of progress is not always apparent to local leaders, for the
official Conn DOT statement as to completion date has been
authoritatively issued. But the completion date is then continually
revised and revised again.
The cause
may be silent, such as two state agencies not in agreement
about some aspect of project impact and without anyone above
them intervening to negotiate. The answer is again for officials
representing the community, both local and state, to show
interest when there is a delay.
Another
possible funding route is to seek a congressional appropriation.
This window opens widest when federal transportation funds
are reauthorized every seven years, with each federal representative
and senator receiving a little piece outside of the regular
funding formulas. The upcoming capacity improvements at I-84
Exit 6 in Danbury were funded with this source.
In years
past it was possible to lobby the Connecticut General Assembly
for 100% state funding for a local road improvement project.
But in recent years state funds have decreased for such purposes.
Rather, state funds for traffic relief and transit improvement
are reserved to serve as the required matching shares for
federal transportation funds. Still, the State Bond Commission
continues to make state funds available for some traffic improvement
projects.
Sometimes
a municipality pursues a project with Conn DOT where the effort
reaches a relatively quick and happy ending. This can occur
when the need is small enough such that DOT District 4 maintenance
forces can complete the needed changes with existing manpower,
without escalating the improvement to the status of a “federal
project” at all.
Overall,
the key to municipal transportation project development is
to acknowledge it as a multi-year process, to which someone
in the local government can be assigned to pursue for the
long haul. For the monitoring of Route 7 improvements in New
Milford, Brookfield and Ridgefield, state representatives
have taken on this “champion” role.
In sum,
success requires strong initial planning, regularly project
monitoring, lobbying and effective use of Conn DOT and HVCEO.
Contents
--
1. -- 2.
--
3. --
4. -- 5.
--
6. --
7.
-- 8.
|