CONNECT
WITH DANBURY INTRO - CONNECT
TO CENTRAL BETHEL
TO
NORTHERN BETHEL - TO
SOUTH BROOKFIELD - DANBURY'S
INTERNAL NEEDS
TO NEW FAIRFIELD - TO
SOUTH NEW MILFORD - TO
NEWTOWN - TO
RIDGEFIELD
Danbury’s
water system has adequate sources of supply to meet current
demands, but the margin of safety of 16% for 2004 and 2005
was very close to the 15% margin of safety recommended by
the Department of Public Health and the Department of Public
Utility Control. The margin of safety varied from 6% to 9%
between 2000 and 2002. As the system is served by surface
supplies, the production can exceed the safe yield to meet
projected maximum month and peak day demands through 2050.
The existing
safe yield is 8.7 MGD, consisting of 4.9 MGD from the West
Lake system (West Lake Reservoir, Boggs Pond, Upper and Lower
Kohanza Reservoirs, and Lake Kenosia Diversion), 3.3 MGD from
the Margerie Lake system (Margerie Lake Reservoir, East Lake
and Padanaram Reservoirs and King Street Diversion) and 0.5
MGD from the Osborne Street Well. The 2005 average day consumption
was 7.48 MGD and 8.21 MGD in 2001.
An additional 1.0 MGD would be needed to provide a 15% margin
of safety for projected average day demands of 8.41 MGD in
2020, and an additional 2.0 MGD for projected average day
demands of 9.29 MGD in 2050. These figures to not include
additional sales to surrounding Towns.
When the
dams and dike for Margerie Reservoir and West Lake Reservoir
were reconstructed several years ago, provisions were made
to allow for the eventual raising of West Lake Reservoir 5
feet and Margerie Reservoir 3 feet. This was to provide additional
storage for diversions from adjacent watersheds.
West Lake Reservoir Dam was constructed to the full height.
Margerie Reservoir Dam and Dike were constructed wide enough
to allow raising, but were not constructed to the full height.
The spillway training wall was constructed to the full height.
At West
Lake Reservoir, water is currently diverted from Lake Kenosia
and the Kenosia Well Field. Raising West Lake Reservoir 5
feet would increase the storage capacity and the safe yield
by 0.6 MGD to 5.5 MGD. The pumping stations and pipelines
are already in place and operating. The additional costs would
be for raising the spillway and raising Middle River Road
along the reservoir. This cost is estimated at about $7.0
million.
At Margerie
Reservoir the potential diversion would be from Lake Candlewood
and would require construction of a pumping station and pipeline.
This is a proposal
with a long history. Raising Margerie Reservoir
3 feet would provide additional storage and would further
increase the safe yield. The cost of raising the dam and dike
would be about $1.4 million.
SEE
MAP OF POTENTIAL DIVERSION
As Lake
Candlewood is a privately owned hydro storage reservoir, Danbury
would have to negotiate an agreement with the owner for access
to the lake and purchase of the water.
The costs
for the Lake Candlewood Diversion pipeline and pumping station
were estimated at $3.6 million. The diversion from Lake Candlewood
assumes no pumping from Memorial Day to Labor Day.
The table below shows the approximate safe yields of the Margerie
System with a 30-inch pipeline and 5, 10 or 15 MGD pumping
capacity from Lake Candlewood, both with and without raising
the reservoir.
APPROXIMATE
SAFE YIELD
OF MARGERIE SYSTEM IN MGD
| |
Lake
Candlewood |
Margerie
Reservoir |
Margerie
Reservoir |
Pumping
Rate (MGD) |
Existing
Level |
Raised
3 Feet |
5 |
6.3 |
6.6 |
10 |
8.0 |
9.3 |
15 |
8.0 |
9.4 |
As
the Margerie Water Filtration Plant has a design capacity
of 5.5 MGD, it would require expansion to accommodate the
higher flows. The plant was built with provisions for adding
two additional filters and an additional dissolved air floatation
clarifier. These additions would increase the capacity to
8.25 MGD. The cost of the expansion has not been determined,
but would be several million dollars.
A Comprehensive
Water Distribution Study of the Danbury System was prepared
in 1987. Along with internal improvements, recommendations
were made for distribution improvements to allow Danbury to
provide "up to 3.0 MGD to surrounding towns to the east."
Neither the distribution system study nor the distribution
system models have been updated.
These
proposed improvements included: 1,600 feet of 20-inch main
in Hayestown Avenue; 4,700 feet of 24-inch main in Tamarack
Avenue, Sherry Lane, and Wixon Road; and 9,800 feet of 20-inch
in Great Plain Road, Stadley Rough Road, Rockwell Road, Rubson
Drive, cross country, Old Brookfield Road, and Federal Road
to the Brookfield town line. To date, of the 16,100 feet needed,
only about 1,200 feet or 7.5% has been installed, this in
Federal Road near Brookfield.
The estimated
cost of the remaining water mains would be about $3,200,000.
If the quantity of water to be provided is significantly less
than 3.0 MGD the costs would also be lower. This is due to
the fact that the need for much of the pipeline would be eliminated
as existing pipelines could be used, or the pipe sizes reduced.
The
end of the 20-inch Danbury water main in Federal Road is currently
about 700 feet from the Brookfield town line. This main is
fed by two 12-inch mains within the Danbury Distribution system.
All
costs were updated with Engineering News Record Construction
Cost Index of 7422 for July 2005.
TOTAL
DANBURY SYSTEM SAFE YIELD
| WELL/SYSTEM |
(MGD) |
| Osborne
Street Well: |
0.5 |
| West
Lake System: |
|
|
Existing Conditions |
4.9 |
|
West Lake Spillway raised |
|
|
5 feet from EL. 610.7 to El. 615.7 |
5.5 |
| Margerie
System:* |
|
|
Existing Conditions |
3.3 |
|
W/5 MGD Lake Candlewood Division* |
6.3 |
|
W/10 MGD Lake Candlewood Division* |
8.0 |
|
W/15 MGD Lake Candlewood Division* |
8.0 |
| *Lake
Candlewood Diversion is a proposed source of supply. |
|
MAIN
WATER PAGE BETHEL
BRIDGEWATER
BROOKFIELD
DANBURY
NEW
FAIRFIELD NEW
MILFORD
NEWTOWN
REDDING
RIDGEFIELD
SHERMAN
|