CONNECT
WITH DANBURY INTRO - CONNECT
TO CENTRAL BETHEL
TO
NORTHERN BETHEL - TO
SOUTH BROOKFIELD - DANBURY'S
INTERNAL NEEDS
TO NEW FAIRFIELD - TO
SOUTH NEW MILFORD - TO
NEWTOWN - TO
RIDGEFIELD
A
water main extension from the Danbury town line north up Federal
Road to the Brookfield Four Corners area would require about
8,000 feet of water main and would cost about $1,500,000.
Once reaching
the Four Corners (Routes 7 and 25 intersection area) it would
connect with the Brookfield Water Company (BWC), which as
of 2005 is just in the process of constructing its water system.
It reportedly has approval for two wells with a combined yield
of 140,000 gallons per day.
An interconnection
has also been constructed to allow the BWC to purchase water
from the United Water System in New Milford to the north.
The piping along Route 7 from the Newbury Village Condominiums
in Brookfield north to the New Milford town line is complete.
A meter building is to be constructed in Brookfield near the
New Milford town line. Thus the BWC’s mains would serve
as an intermediary to any regional connection between Danbury,
Brookfield and New Milford.
SEE
MAP OF POTENTIAL CONNECTION
Purchases
of water by BWC from United Water will be limited to less
than 50,000 gallons per day unless a DEP Diversion Permit
is obtained in the future for a higher amount. There are no
plans to obtain the permit. The BWC does not have a Water
Supply Plan or projections for future use. Robert Parker,
BWC President, reported that the current sources are expected
to be adequate for the next 10 years.
Note that
the United Water System is at HGL 463, which is higher than
the BWC System HGL 403. Thus the BWC pressure will have to
be increased to HGL 463 or a pressure reducing valve installed
in order to serve the BWC System from the United Water System.
As noted
above the BWC System operates off a hydropneumatic tank, which
does not provide fire protection. An atmospheric tank would
be required in Brookfield to provide adequate storage for
fire protection. The cost of the storage tank would be range
from $500,000 to $1,000,000.
The United
Water Connecticut New Milford System currently has adequate
source of supply, but the system demands are growing rapidly
and are projected to have margin of safety of less than 15%
for peak day demands after 2020.
The existing
safe yield is 1.822 MGD (1.336 MGD without Well No. 5) and
the maximum available water is 2.430 (1.782 MGD without Well
No. 5). The 2001 consumption (the highest recorded to date)
was 1.235 MGD with a margin of safety of 1.08, maximum month
was 1.366 MGD with a margin of safety of 0.95, and peak day
was 1.852 with a margin of safety of 0.96. Well No. 5 is in
use, but can not be currently included in the available supply
calculations because the ground around the well is below the
100-year flood level. United Water Company is working on corrective
measures for Well No. 5 and expects to have the improvements
made within the next two years.
With Well
No. 5, the water system would have adequate margin of safety
through 2020. In 2004, the average day demand was 1.08 MGD,
the maximum month was 1.21 MGD, and the peak day was 1.52
MGD.
For 2050,
if additional wells are not developed in New Milford, the
United Water System would need 0.25 MGD for average day, 0.47
MGD for maximum month, and 0.67 MGD for peak day, in order
to provide a margin of safety of 1.15.
MAIN
WATER PAGE BETHEL
BRIDGEWATER
BROOKFIELD
DANBURY
NEW
FAIRFIELD NEW
MILFORD
NEWTOWN
REDDING
RIDGEFIELD
SHERMAN
|